Power plant Timelkam / Austria




- Entry from ground to pump house DN 2,000 – 1,200
- Delievery and insertion of a 21 m prefabricated spool
- Distributor prefabrication in GRP – with PVC lining
- Buried pipe DN 2,000, partly filled, at entry to power house
- Collector with dished and nozzle outflow
Client
VAM Anlagentechnik und Montagen
General Contractor
Siemens
Scope of services
Planning, delivery, prefabrication and supervision
Component
Main and secondary cooling water pipelines
Plant
Gas and steam power plant
Material
Epoxy vinyl ester resin, reinforced with glass fibres and GRP with PVC liner
Installation
Overground and underground
Medium
Cooling water
Pressure stages
PN 6 / -0.9 bar
Nominal diameter
DIN 25 – 2,000